Every stage, timed
- Design and ordering: one to two weeks.
- Making the units: two to six weeks; bespoke takes four to six weeks of workshop time.
- Fitting: three to seven days.
- Stone worktop: templated after the units go in, fitted a week or two later.
- Tiling, plumbing, electrics: the job runs to two to three weeks on site.
A made-to-measure kitchen is usually fitted within about 12 weeks of signing off the design. A respray takes one to five days.
How long you're without a kitchen
About a week for the old one out and the new one in, a little longer with stone. Set up a kettle and a microwave in another room.
What slows it down
- Changing the design after it's ordered.
- Moving the sink, cooker or a wall: the plumber, electrician or builder comes first.
- The run-up to Christmas.

Take a photo, pick a style, colour and worktop, and our free Studio draws it on your room.
Design my kitchen, freeQuestions people ask
How long does a kitchen renovation take in Ireland?
Four to eight weeks from design to finished, with three to seven days of fitting on site.
How long will I be without a kitchen?
About a week, a little longer with a stone worktop.